Eland Solar & Storage Center, Phase 2 Hy ππ€ 
Status 
operation 
Country / State / Closest City 
πΊπΈ usa / california / 
Dates
    
        
            
                | First heard | 
                2020-09 | 
            
            
                | Construction start | 
                2024-12 | 
            
            
                | Operation start | 
                2025-07 | 
            
            
                | Estimated start | 
                2023-07 | 
            
            
            
                | Construction time | 
                
                    
                    7 months -> 85 MWh/m
                    
                 | 
            
        
     
 
Capacity in MWh 
    600
    
Maximum Power in MW 
150
Manufacturer 
tesla 
Type / Number of Packs / Cells 
megapack 2XL /  / 
Customer / Owner / Developer
 / 69SV 8me LLC / Arevon 
Use case 
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:35.198008+-117.994 
Coordinates 
    35.198008, -117.994 
    
 β
 The site is known, coords are +/- 1 kilometer
Notes 
    
     
     
Project website 
  
 Sources 
    
    https://twitter.com/SawyerMerritt/status/1760848348607594844  
    
    https://renewablesnow.com/news/arevon-secures-over-usd-1bn-for-california-solar-plus-storage-project-849335/  
    
    https://x.com/Tesla_Megapack/status/1794120454883659833  
     
 Internal / External id 
    164 / 61169
    
 U.S. EIA data 
The government data source for this battery is the U.S. Energy Information Administration (EIA)
    https://www.eia.gov/electricity/monthly/
Info from the 
2025-09 report (Project first appeared in the 
2020-09 report):
Plant Name / State
Eland Solar & Storage Center, Phase 2 Hy / CA
go live / power 
2025-07 / 150MW
status / status verbose
operation / operation 
Plant id / generator id 
61169 / 61169
Entity name / entity id 
69SV 8me LLC / 60798
Changes:
    2025-09
    
        status: construction -> operation πΎ π πΈ
    
        status_verbose: (V) Under construction, more than 50 percent complete -> operation 
     
    
2025-06
    
        date: 2025-05 -> 2025-07 delayed by 
2 months
     
    
2025-05
    
        date: 2025-03 -> 2025-05 delayed by 
2 months
     
    
2024-12
    
        status: planning -> construction ποΈ
    
        status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete 
     
    
2024-10
    
        plant name: Eland Solar & Storage Center, Phase 2 Hybrid -> Eland Solar & Storage Center, Phase 2 Hy 
     
    
2024-01
    
        date: 2024-11 -> 2025-03 delayed by 
4 months
     
    
2023-01
    
        date: 2023-11 -> 2024-11 delayed by 
12 months
     
    
2022-01
    
        status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction 
    
        date: 2023-07 -> 2023-11 delayed by 
4 months