RedSun PV and BESS πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2024-08
Construction start
Operation start
Estimated start 2027-06
Construction time
Capacity in MWh
168
πŸ“ This is an estimate
Maximum Power in MW
84
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Gransolar Texas Twenty Two LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.313285042978755+-95.17116336610111
Coordinates
33.313285042978755, -95.17116336610111
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1617 / 67782

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-08 report):

Plant Name / State
RedSun PV and BESS / TX
go live / power
2027-06 / 84MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
67782 / GS22B
Entity name / entity id
Gransolar Texas Twenty Two LLC / 66380
Changes: