Thunder Wolf Energy Center Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / colorado /
Dates
First heard |
2020-09 |
Construction start |
2022-02 |
Operation start |
2023-06 |
Estimated start |
2022-12 |
Construction time |
16 months -> 12 MWh/m
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Thunder Wolf Energy Center, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.742576+-102.716675
Coordinates
40.742576, -102.716675
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
205 / 63776
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Thunder Wolf Energy Center Hybrid / CO
go live / power
2023-06 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63776 / TW100
Entity name / entity id
Thunder Wolf Energy Center, LLC / 63454
Changes:
2023-08
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-07
date: 2023-05 -> 2023-06 delayed by
1 month
2023-03
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-11
date: 2022-12 -> 2023-05 delayed by
5 months
2022-02
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete