Brazos Bend BESS, LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-07
Construction start 2023-10
Operation start 2024-09
Estimated start 2024-06
Construction time 11 months -> 18 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Brazos Bend BESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.428714606461256+-95.3514246343362
Coordinates
33.428714606461256, -95.3514246343362
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1031 / 66690

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2023-07 report):

Plant Name / State
Brazos Bend BESS, LLC / TX
go live / power
2024-09 / 100MW
status / status verbose
operation / operation
Plant id / generator id
66690 / BEND
Entity name / entity id
Brazos Bend BESS, LLC / 65696
Changes:
2024-11
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-09
date: 2024-07 -> 2024-09 delayed by 2 months
2024-08
date: 2024-06 -> 2024-07 delayed by 1 month
2024-06
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2024-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-10
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete