Cranberry Point Energy Storage πŸ“ŠπŸ‘€

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / massachusetts / Carver
Dates
First heard 2020-09
Construction start
Operation start
Estimated start 2025-05
Construction time
Capacity in MWh
300
Maximum Power in MW
150
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / /
Customer / Owner / Developer
/ Cranberry Point Energy Storage LLC / Plus Power
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.896693+-70.786639
Coordinates
41.896693, -70.786639
βœ… Coords are exact (+/- 50m)
Notes
got the info about tesla as manufacturer from twitter thread and FAQ on the project website
Project website
https://cranberrypointenergystorage.com/
Sources
https://www.greentechmedia.com/articles/read/plus-power-breaks-open-new-england-market-for-massive-batteries
https://twitter.com/SharifaDarani/status/1612314447074439168
Internal / External id
113 / 62844

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Cranberry Point Energy Storage / MA
go live / power
2025-05 / 150MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
62844 / NA
Entity name / entity id
Cranberry Point Energy Storage LLC / 62733
Changes:
2023-03
date: 2024-06 -> 2025-05 delayed by 11 months
2021-03
date: 2023-05 -> 2024-06 delayed by 13 months