Byrd Ranch Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2022-02 |
Construction start |
2022-03 |
Operation start |
2022-11 |
Estimated start |
2022-08 |
Construction time |
8 months -> 12 MWh/m
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Byrd Ranch Storage LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.349606255901264+-94.95198089749223
Coordinates
33.349606255901264, -94.95198089749223
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
579 / 65259
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2022-02
report):
Plant Name / State
Byrd Ranch Storage / TX
go live / power
2022-11 / 50MW
status / status verbose
operation / operation
Plant id / generator id
65259 / P1
Entity name / entity id
Byrd Ranch Storage LLC / 64564
Changes:
2023-01
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2022-10 -> 2022-11 delayed by
1 month
2022-11
date: 2022-09 -> 2022-10 delayed by
1 month
2022-10
date: 2022-08 -> 2022-09 delayed by
1 month
2022-03
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete