TX12 Silicon Hill Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-07
Construction start
Operation start 2022-10
Estimated start
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.313285042978755+-95.17116336610111
Coordinates
33.313285042978755, -95.17116336610111
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
717 / 65695

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2022-07 report):

Plant Name / State
TX12 Silicon Hill Storage / TX
go live / power
2022-10 / 100MW
status / status verbose
operation / operation
Plant id / generator id
65695 / TX12
Entity name / entity id
Key Capture Energy / 63289
Changes:
2022-12
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-11
date: 2022-09 -> 2022-10 delayed by 1 month