Chalan πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2025-04 |
Construction start |
|
Operation start |
|
Estimated start |
2026-12 |
Construction time |
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ OE_CHA, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.48004900000001
Coordinates
41.122677, -121.48004900000001
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1690 / 68672
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-04
report (Project first appeared in the
2025-04
report):
Plant Name / State
Chalan / CA
go live / power
2026-12 / 25MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
68672 / CHA_B
Entity name / entity id
OE_CHA, LLC / 67016
Changes: