Mohave Energy - Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2024-02
Construction start
Operation start 2023-09
Estimated start
Construction time
Capacity in MWh
30
πŸ“ This is an estimate
Maximum Power in MW
15
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Mohave Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.58187920440347+-110.02764099100999
Coordinates
36.58187920440347, -110.02764099100999
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1308 / 67178

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2024-02 report):

Plant Name / State
Mohave Energy - Hybrid / AZ
go live / power
2023-09 / 15MW
status / status verbose
operation / operation
Plant id / generator id
67178 / MEBA
Entity name / entity id
Mohave Energy / 66056