Roadrunner, LLC Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2021-06
Construction start 2022-01
Operation start 2023-07
Estimated start
Construction time 18 months -> 5 MWh/m
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Roadrunner Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.27525537493651+-95.3315331949425
Coordinates
33.27525537493651, -95.3315331949425
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
254 / 62561

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-06 report):

Plant Name / State
Roadrunner, LLC Hybrid / TX
go live / power
2023-07 / 50MW
status / status verbose
operation / operation
Plant id / generator id
62561 / BA
Entity name / entity id
Roadrunner Solar, LLC / 62047
Changes:
2023-09
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-08
date: 2023-06 -> 2023-07 delayed by 1 month
2023-06
date: 2023-05 -> 2023-06 delayed by 1 month
2023-05
date: 2023-03 -> 2023-05 delayed by 2 months
2023-03
date: 2023-01 -> 2023-03 delayed by 2 months
2022-12
date: 2022-11 -> 2023-01 delayed by 2 months
2022-10
date: 2022-09 -> 2022-11 delayed by 2 months
2022-09
date: 2022-08 -> 2022-09 delayed by 1 month
2022-08
date: 2022-06 -> 2022-08 delayed by 2 months
2022-06
date: 2022-05 -> 2022-06 delayed by 1 month
2022-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-01
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete