McFarland B Solar and Storage πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2023-06 |
Construction start |
2023-09 |
Operation start |
|
Estimated start |
2024-09 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.58187920440347+-110.02764099100999
Coordinates
36.58187920440347, -110.02764099100999
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1008 / 66637
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-06
report):
Plant Name / State
McFarland B Solar and Storage / AZ
go live / power
2024-09 / 150MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66637 / BESS
Entity name / entity id
AES Clean Energy / 64904
Changes:
2024-07
date: 2024-08 -> 2024-09 delayed by
1 month
2024-06
date: 2024-07 -> 2024-08 delayed by
1 month
2024-03
date: 2024-05 -> 2024-07 delayed by
2 months
2023-11
date: 2023-12 -> 2024-05 delayed by
5 months
2023-09
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete