Superstition Energy Storage πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona / Gilbert
Dates
First heard 2023-03
Construction start 2024-04
Operation start 2024-06-27
Estimated start 2024-06
Construction time 2 months -> 180 MWh/m
Capacity in MWh
360
Maximum Power in MW
90
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / /
Customer / Owner / Developer
Salt River Project / Superstition Energy Storage, LLC / Plus Power
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.358927+-111.831039
Coordinates
33.358927, -111.831039
βœ… Coords are exact (+/- 50m)
Notes

Project website
https://www.superstitionenergystorage.com/about
Sources
https://www.energy-storage.news/arizona-utility-srp-to-arrive-at-800mw-battery-storage-by-mid-2024-with-two-new-deals/
https://twitter.com/SharifaDarani/status/1612314447074439168
https://electrek.co/2024/06/27/tesla-megapack-project-giant-online-arizona/
Internal / External id
852 / 66333

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-03 report):

Plant Name / State
Superstition Energy Storage / AZ
go live / power
2024-06 / 90MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66333 / BESS4
Entity name / entity id
Superstition Energy Storage, LLC / 65419
Changes:
2024-04
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete
2023-08
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction