Condor Energy Storage LLC ππ€
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2023-03 |
Construction start |
2023-10 |
Operation start |
2024-05 |
Estimated start |
|
Construction time |
7 months -> 114 MWh/m
|
Capacity in MWh
800
Maximum Power in MW
200
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / /
Customer / Owner / Developer
arevon / Condor Energy Storage LLC / tenaska
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:34.020505+-117.332255
Coordinates
34.020505, -117.332255
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
https://arevonenergy.com/location/condor/
Sources
https://arevonenergy.com/new-utility-scale-battery-storage-facility-planned-for-city-of-grand-terrace/
Internal / External id
864 / 66285
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-03
report):
Plant Name / State
Condor Energy Storage LLC / CA
go live / power
2024-05 / 200MW
status / status verbose
operation / operation
Plant id / generator id
66285 / COND1
Entity name / entity id
Condor Energy Storage LLC / 65397
Changes:
2024-07
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2024-06
date: 2024-04 -> 2024-05 delayed by
1 month
2024-02
date: 2024-03 -> 2024-04 delayed by
1 month
2023-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-10
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2024-08 -> 2024-03 accelerated by
5 months