Painter Energy Storage πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2021-03 |
Construction start |
2022-06 |
Operation start |
|
Estimated start |
2024-10 |
Construction time |
|
Capacity in MWh
20
π This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Painter Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.24258519146767+-121.13500953314751
Coordinates
41.24258519146767, -121.13500953314751
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
182 / 62729
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2021-03
report):
Plant Name / State
Painter Energy Storage / CA
go live / power
2024-10 / 10MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
62729 / PAIN1
Entity name / entity id
Painter Energy Storage, LLC / 62646
Changes:
2024-07
date: 2024-09 -> 2024-10 delayed by
1 month
2024-06
date: 2024-07 -> 2024-09 delayed by
2 months
2024-05
date: 2024-06 -> 2024-07 delayed by
1 month
2024-04
date: 2024-05 -> 2024-06 delayed by
1 month
2024-03
date: 2024-04 -> 2024-05 delayed by
1 month
2023-12
date: 2023-12 -> 2024-04 delayed by
4 months
2023-11
date: 2023-11 -> 2023-12 delayed by
1 month
2023-10
date: 2023-10 -> 2023-11 delayed by
1 month
2023-05
date: 2023-08 -> 2023-10 delayed by
2 months
2023-04
date: 2023-06 -> 2023-08 delayed by
2 months
2023-03
date: 2023-04 -> 2023-06 delayed by
2 months
2023-02
date: 2023-03 -> 2023-04 delayed by
1 month
2022-07
date: 2022-08 -> 2023-03 delayed by
7 months
2022-06
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2022-07 -> 2022-08 delayed by
1 month
2022-04
date: 2022-09 -> 2022-07 accelerated by
2 months
mw: 40 -> 10
2022-01
status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
2021-08
date: 2021-12 -> 2022-09 delayed by
9 months