AES Waikoloa Solar Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / hawaii /
Dates
First heard |
2020-09 |
Construction start |
2022-08 |
Operation start |
2023-04 |
Estimated start |
2022-11 |
Construction time |
8 months -> 7 MWh/m
|
Capacity in MWh
60
π This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Distributed Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:19.542269538483755+-155.56408453169715
Coordinates
19.542269538483755, -155.56408453169715
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
213 / 63900
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
AES Waikoloa Solar Hybrid / HI
go live / power
2023-04 / 30MW
status / status verbose
operation / operation
Plant id / generator id
63900 / KLOAB
Entity name / entity id
AES Distributed Energy / 61012
Changes:
2023-06
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-04
date: 2023-02 -> 2023-04 delayed by
2 months
2023-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-10
date: 2022-11 -> 2023-02 delayed by
3 months
2022-08
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete