Buena Vista Energy LLC πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-02
Construction start
Operation start
Estimated start 2026-12
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Leeward Asset Management, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.98192063558832+-121.3457835151675
Coordinates
40.98192063558832, -121.3457835151675
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
934 / 56446

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-02 report):

Plant Name / State
Buena Vista Energy LLC / CA
go live / power
2026-12 / 100MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
56446 / BVBAT
Entity name / entity id
Leeward Asset Management, LLC / 50123
Changes: