Trenton πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / florida /
Dates
First heard 2020-10
Construction start
Operation start 2021-12
Estimated start
Construction time
Capacity in MWh
22
πŸ“ This is an estimate
Maximum Power in MW
11
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Duke Energy Florida, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:30.235434204403475+-82.28990899100998
Coordinates
30.235434204403475, -82.28990899100998
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
208 / 63995

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-10 report):

Plant Name / State
Trenton / FL
go live / power
2021-12 / 11MW
status / status verbose
operation / operation
Plant id / generator id
63995 / ES1
Entity name / entity id
Duke Energy Florida, LLC / 6455
Changes:
2022-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
date: 2022-01 -> 2021-12 accelerated by 1 month
2022-01
date: 2021-11 -> 2022-01 delayed by 2 months
2021-12
date: 2021-10 -> 2021-11 delayed by 1 month
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-10
date: 2021-08 -> 2021-09 delayed by 1 month
2021-08
date: 2021-07 -> 2021-08 delayed by 1 month
2021-07
date: 2021-06 -> 2021-07 delayed by 1 month
2021-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete