Vonore Battery Energy Storage System πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / tennessee /
Dates
First heard 2021-01
Construction start 2023-05
Operation start
Estimated start 2024-03
Construction time
Capacity in MWh
40
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Tennessee Valley Authority /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.315642+-83.002733
Coordinates
36.315642, -83.002733
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
240 / 64255

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-01 report):

Plant Name / State
Vonore Battery Energy Storage System / TN
go live / power
2024-03 / 20MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
64255 / VBESS
Entity name / entity id
Tennessee Valley Authority / 18642
Changes:
2023-12
date: 2023-12 -> 2024-03 delayed by 3 months
2023-05
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
date: 2023-08 -> 2023-12 delayed by 4 months
2022-04
date: 2022-07 -> 2023-08 delayed by 13 months