Sierra Energy Storage, LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2020-09 |
Construction start |
2022-09 |
Operation start |
|
Estimated start |
2024-06 |
Construction time |
|
Capacity in MWh
20
π This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Engie North America /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.300049
Coordinates
41.122677, -121.300049
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
200 / 61803
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2020-09
report):
Plant Name / State
Sierra Energy Storage, LLC / CA
go live / power
2024-06 / 10MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
61803 / 10003
Entity name / entity id
Engie North America / 56201
Changes:
2024-06
date: 2024-04 -> 2024-06 delayed by
2 months
2024-05
date: 2024-03 -> 2024-04 delayed by
1 month
2024-03
entity id: 63883 -> 56201
entity name: Broad Reach Power -> Engie North America
2024-01
date: 2023-12 -> 2024-03 delayed by
3 months
2023-10
date: 2023-09 -> 2023-12 delayed by
3 months
2023-06
date: 2023-06 -> 2023-09 delayed by
3 months
2023-03
date: 2023-03 -> 2023-06 delayed by
3 months
2023-02
date: 2023-02 -> 2023-03 delayed by
1 month
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-11
entity id: 59380 -> 63883
entity name: Enel Green Power NA, Inc. -> Broad Reach Power
2022-10
date: 2022-12 -> 2023-02 delayed by
2 months
2022-09
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete