Noria Hondo Solar (Hybrid) πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2022-03 |
Construction start |
|
Operation start |
|
Estimated start |
2025-09 |
Construction time |
|
Capacity in MWh
150
π This is an estimate
Maximum Power in MW
75
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Noria Hondo Solar LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.58101561449517+-95.448185670785
Coordinates
33.58101561449517, -95.448185670785
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
628 / 65344
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2022-03
report):
Plant Name / State
Noria Hondo Solar (Hybrid) / TX
go live / power
2025-09 / 75MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
65344 / 66149
Entity name / entity id
Noria Hondo Solar LLC / 64674
Changes:
2023-11
date: 2024-09 -> 2025-09 delayed by
12 months