Beehive Energy Storage πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2024-02 |
Construction start |
|
Operation start |
|
Estimated start |
2025-09 |
Construction time |
|
Capacity in MWh
500
π This is an estimate
Maximum Power in MW
250
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Beehive Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.60301761713374+-109.97577292885305
Coordinates
36.60301761713374, -109.97577292885305
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1307 / 67184
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-02
report):
Plant Name / State
Beehive Energy Storage / AZ
go live / power
2025-09 / 250MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
67184 / BHV1
Entity name / entity id
Beehive Energy Storage, LLC / 66053
Changes: