Victory Pass πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-08
Construction start 2022-10
Operation start 2024-03
Estimated start 2022-11
Construction time 17 months -> 5 MWh/m
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Victory Pass I, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.183862364886245+-121.48835819022644
Coordinates
41.183862364886245, -121.48835819022644
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
709 / 65743

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-08 report):

Plant Name / State
Victory Pass / CA
go live / power
2024-03 / 50MW
status / status verbose
operation / operation
Plant id / generator id
65743 / VCTBA
Entity name / entity id
Victory Pass I, LLC / 64995
Changes:
2024-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-10
date: 2023-12 -> 2024-03 delayed by 3 months
2023-09
date: 2023-11 -> 2023-12 delayed by 1 month
2023-06
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-10
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2022-11 -> 2023-11 delayed by 12 months