Estonian Solar Project, LLC πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-09
Construction start 2024-02
Operation start
Estimated start 2024-08
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Enel Green Power Estonian Solar Project, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.291825270367276+-95.05014930955251
Coordinates
33.291825270367276, -95.05014930955251
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1058 / 66872

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-09 report):

Plant Name / State
Estonian Solar Project, LLC / TX
go live / power
2024-08 / 100MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
66872 / BESS
Entity name / entity id
Enel Green Power Estonian Solar Project, LLC / 65799
Changes:
2024-05
date: 2024-03 -> 2024-08 delayed by 5 months
2024-02
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (TS) Construction complete, but not yet in commercial operation
date: 2024-10 -> 2024-03 accelerated by 7 months
2023-11
date: 2024-04 -> 2024-10 delayed by 6 months