TX19 River Valley Storage 1 πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2022-07 |
Construction start |
|
Operation start |
2023-07 |
Estimated start |
2022-12 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.57578923408578+-95.23388382472001
Coordinates
33.57578923408578, -95.23388382472001
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
724 / 65699
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2022-07
report):
Plant Name / State
TX19 River Valley Storage 1 / TX
go live / power
2023-07 / 50MW
status / status verbose
operation / operation
Plant id / generator id
65699 / TX19
Entity name / entity id
Key Capture Energy / 63289
Changes:
2023-09
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-07
date: 2023-05 -> 2023-07 delayed by
2 months
2023-05
date: 2023-03 -> 2023-05 delayed by
2 months
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2023-01 -> 2023-03 delayed by
2 months
2022-11
date: 2022-12 -> 2023-01 delayed by
1 month