Roseland Solar Project, LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-03
Construction start 2022-08
Operation start 2023-07
Estimated start
Construction time 11 months -> 10 MWh/m
Capacity in MWh
118
πŸ“ This is an estimate
Maximum Power in MW
59
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Enel Green Power Roseland Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.527600044661234+-95.49978945087824
Coordinates
33.527600044661234, -95.49978945087824
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
629 / 65028

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-03 report):

Plant Name / State
Roseland Solar Project, LLC / TX
go live / power
2023-07 / 59MW
status / status verbose
operation / operation
Plant id / generator id
65028 / ROSEB
Entity name / entity id
Enel Green Power Roseland Solar, LLC / 64438
Changes:
2023-09
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-08
date: 2023-06 -> 2023-07 delayed by 1 month
2023-06
date: 2023-05 -> 2023-06 delayed by 1 month
2023-05
date: 2023-03 -> 2023-05 delayed by 2 months
2023-04
date: 2023-02 -> 2023-03 delayed by 1 month
2023-03
date: 2023-01 -> 2023-02 delayed by 1 month
2023-01
date: 2022-12 -> 2023-01 delayed by 1 month
2022-12
date: 2022-11 -> 2022-12 delayed by 1 month
2022-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-08
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete