Longbow BESS, LLC πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2024-01 |
Construction start |
|
Operation start |
2024-10 |
Estimated start |
2024-07 |
Construction time |
|
Capacity in MWh
348
π This is an estimate
Maximum Power in MW
174
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Longbow BESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.65154984477027+-95.54526771010998
Coordinates
33.65154984477027, -95.54526771010998
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1188 / 67083
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-01
report):
Plant Name / State
Longbow BESS, LLC / TX
go live / power
2024-10 / 174MW
status / status verbose
operation / operation
Plant id / generator id
67083 / LBBES
Entity name / entity id
Longbow BESS, LLC / 65984
Changes:
2024-12
status: construction -> operation πΎ π πΈ
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2024-11
date: 2024-09 -> 2024-10 delayed by
1 month
2024-10
date: 2024-08 -> 2024-09 delayed by
1 month
2024-08
date: 2024-07 -> 2024-08 delayed by
1 month