Wheatridge Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / oregon /
Dates
First heard 2020-09
Construction start 2021-12
Operation start 2022-03
Estimated start
Construction time 3 months -> 20 MWh/m
Capacity in MWh
60
πŸ“ This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Wheatridge Wind Holdings, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:45.52252661545126+-117.89061341879585
Coordinates
45.52252661545126, -117.89061341879585
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
239 / 62745

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Wheatridge Hybrid / OR
go live / power
2022-03 / 30MW
status / status verbose
operation / operation
Plant id / generator id
62745 / BTRY
Entity name / entity id
Wheatridge Wind Holdings, LLC / 62668
Changes:
2022-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-01
date: 2021-12 -> 2022-03 delayed by 3 months
2021-12
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete
2021-01
entity name: Wheatridge Wind Energy, LLC -> Wheatridge Wind Holdings, LLC