Hornshadow Solar, LLC πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / utah /
Dates
First heard |
2024-05 |
Construction start |
|
Operation start |
|
Estimated start |
2025-06 |
Construction time |
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hornshadow Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.53024549915876+-109.81897476197224
Coordinates
40.53024549915876, -109.81897476197224
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1373 / 67497
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-05
report):
Plant Name / State
Hornshadow Solar, LLC / UT
go live / power
2025-06 / 25MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
67497 / HSESS
Entity name / entity id
Hornshadow Solar, LLC / 66059