Bottleneck Energy Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-08
Construction start
Operation start
Estimated start 2024-07
Construction time
Capacity in MWh
160
πŸ“ This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ VESI 12 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.94954736320376+-121.17426295600941
Coordinates
40.94954736320376, -121.17426295600941
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1037 / 66757

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-08 report):

Plant Name / State
Bottleneck Energy Storage / CA
go live / power
2024-07 / 80MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66757 / BN1
Entity name / entity id
VESI 12 LLC / 65754
Changes:
2024-03
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2024-04 -> 2024-07 delayed by 3 months