Lone Star Solar πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / south carolina /
Dates
First heard 2022-04
Construction start 2023-08
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
132
πŸ“ This is an estimate
Maximum Power in MW
66
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Lone Star Solar /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:34.78959784072874+-79.6594265329819
Coordinates
34.78959784072874, -79.6594265329819
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
683 / 62235

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-04 report):

Plant Name / State
Lone Star Solar / SC
go live / power
2024-12 / 66MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
62235 / 50
Entity name / entity id
Lone Star Solar / 61752
Changes:
2024-02
date: 2023-12 -> 2024-12 delayed by 12 months
2023-08
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete