Bear Canyon πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-06
Construction start 2023-12
Operation start
Estimated start 2024-03
Construction time
Capacity in MWh
26
πŸ“ This is an estimate
Maximum Power in MW
13
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Bear Canyon Energy Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.14183605365125+-121.2410834959897
Coordinates
41.14183605365125, -121.2410834959897
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1021 / 66650

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-06 report):

Plant Name / State
Bear Canyon / CA
go live / power
2024-03 / 13MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66650 / BC1
Entity name / entity id
Bear Canyon Energy Storage / 65674
Changes:
2024-02
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-12
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete