Solar Blue πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-03
Construction start
Operation start 2023-12
Estimated start 2023-09
Construction time
Capacity in MWh
450
πŸ“ This is an estimate
Maximum Power in MW
225
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Westlands Solar Blue (OZ) Owner, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.20858372443624+-121.56444271153005
Coordinates
41.20858372443624, -121.56444271153005
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
949 / 63848

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-03 report):

Plant Name / State
Solar Blue / CA
go live / power
2023-12 / 225MW
status / status verbose
operation / operation
Plant id / generator id
63848 / BESS1
Entity name / entity id
Westlands Solar Blue (OZ) Owner, LLC / 63525
Changes:
2024-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2024-01
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
date: 2023-09 -> 2023-11 delayed by 2 months