OE_MS5 πππ
Status
cancelled
Country / State / Closest City
πΊπΈ usa / mississippi /
Dates
First heard |
2021-05 |
Construction start |
2023-06 |
Operation start |
|
Estimated start |
2023-12 |
Month disappeared |
2024-02 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ OE_MS5 /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:32.73144896119256+-89.67661057247251
Coordinates
32.73144896119256, -89.67661057247251
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
222 / 64529
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-01
report (Project first appeared in the
2021-05
report):
Plant Name / State
OE_MS5 / MS
go live / power
2023-12 / 50MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
64529 / MS5_S
Entity name / entity id
OE_MS5 / 64087
Changes:
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-06
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-12
date: 2022-12 -> 2023-12 delayed by
12 months
2024-02
This project disappeared in the
2024-02
report.
That's why the status was set to
cancelled