Kearny North Energy Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2021-06
Construction start 2021-07
Operation start 2022-02
Estimated start 2021-10
Construction time 7 months -> 2 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ San Diego Gas & Electric Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.148539551100875+-121.26445225224751
Coordinates
41.148539551100875, -121.26445225224751
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
202 / 64612

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2021-06 report):

Plant Name / State
Kearny North Energy Storage / CA
go live / power
2022-02 / 10MW
status / status verbose
operation / operation
Plant id / generator id
64612 / KNES
Entity name / entity id
San Diego Gas & Electric Co / 16609
Changes:
2022-04
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-03
date: 2022-01 -> 2022-02 delayed by 1 month
2022-02
date: 2021-12 -> 2022-01 delayed by 1 month
2022-01
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2021-12
date: 2021-11 -> 2021-12 delayed by 1 month
2021-11
date: 2021-10 -> 2021-11 delayed by 1 month
2021-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2021-09 -> 2021-10 delayed by 1 month
2021-08
date: 2021-06 -> 2021-09 delayed by 3 months
2021-07
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete