Cascade Energy Storage, LLC πŸ“πŸ“ŠπŸ‘€

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california / Stockton
Dates
First heard 2020-09
Construction start 2022-05
Operation start
Estimated start 2024-01
Construction time
Capacity in MWh
100
Maximum Power in MW
25
Manufacturer
SYL Battery (Risen Energy)
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
PG&E / Broad Reach Power / Plus Power
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:37.921103+-121.24114
Coordinates
37.921103, -121.24114
πŸ“ Coords not known
Notes

Project website
Sources
https://ceqanet.opr.ca.gov/2020090414/2
https://www.energy-storage.news/broad-reach-power-orders-118mwh-ess-equipment-for-california-project-from-syl-battery/
Internal / External id
112 / 61801

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Cascade Energy Storage, LLC / CA
go live / power
2024-01 / 25MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
61801 / 10002
Entity name / entity id
Broad Reach Power / 63883
Changes:
2024-02
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2024-01
date: 2023-12 -> 2024-01 delayed by 1 month
2023-12
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
date: 2023-09 -> 2023-11 delayed by 2 months
2023-10
date: 2023-08 -> 2023-09 delayed by 1 month
2023-08
date: 2023-07 -> 2023-08 delayed by 1 month
2023-04
date: 2023-04 -> 2023-07 delayed by 3 months
2023-02
date: 2023-03 -> 2023-04 delayed by 1 month
2023-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-10
date: 2022-12 -> 2023-03 delayed by 3 months
2022-05
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2021-04
entity id: 59380 -> 63883
entity name: Enel Green Power NA, Inc. -> Broad Reach Power