Hecate Energy Desert Storage 1 LLC πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-06
Construction start 2023-05
Operation start
Estimated start 2025-01
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hecate Energy Desert Storage 1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.08505874385328+-121.35182608763999
Coordinates
41.08505874385328, -121.35182608763999
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
712 / 65635

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-06 report):

Plant Name / State
Hecate Energy Desert Storage 1 LLC / CA
go live / power
2025-01 / 10MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65635 / HEDS1
Entity name / entity id
Hecate Energy Desert Storage 1 LLC / 64937
Changes:
2024-07
date: 2024-05 -> 2025-01 delayed by 8 months
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2024-01 -> 2024-05 delayed by 4 months
2023-12
date: 2023-12 -> 2024-01 delayed by 1 month
2023-11
date: 2023-11 -> 2023-12 delayed by 1 month
2023-08
date: 2023-09 -> 2023-11 delayed by 2 months
2023-05
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-02
date: 2023-05 -> 2023-09 delayed by 4 months
2022-11
date: 2023-04 -> 2023-05 delayed by 1 month
2022-09
date: 2022-12 -> 2023-04 delayed by 4 months