Azure Sky Solar πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2020-09
Construction start
Operation start 2022-06
Estimated start
Construction time
Capacity in MWh
154
πŸ“ This is an estimate
Maximum Power in MW
77
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Azure Sky Solar Project, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.539960724436234+-95.53783171153005
Coordinates
33.539960724436234, -95.53783171153005
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
249 / 63905

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Azure Sky Solar / TX
go live / power
2022-06 / 77MW
status / status verbose
operation / operation
Plant id / generator id
63905 / ASKYB
Entity name / entity id
Azure Sky Solar Project, LLC / 63571
Changes:
2022-08
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-07
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2022-06
date: 2022-05 -> 2022-06 delayed by 1 month
2022-04
date: 2022-02 -> 2022-05 delayed by 3 months
2022-02
date: 2021-12 -> 2022-02 delayed by 2 months
2022-01
date: 2021-11 -> 2021-12 delayed by 1 month
2021-12
date: 2021-10 -> 2021-11 delayed by 1 month
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-10
date: 2021-08 -> 2021-09 delayed by 1 month
2021-08
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete