Luna Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start 2021-04
Operation start 2022-06
Estimated start
Construction time 14 months -> 14 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Distributed Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.440049
Coordinates
41.122677, -121.440049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
170 / 63685

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Luna Storage / CA
go live / power
2022-06 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63685 / LUNA
Entity name / entity id
AES Distributed Energy / 61012
Changes:
2022-08
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-07
date: 2022-05 -> 2022-06 delayed by 1 month
2022-05
date: 2022-04 -> 2022-05 delayed by 1 month
2022-04
entity id: 63403 -> 61012
entity name: Luna Storage, LLC -> AES Distributed Energy
2021-12
date: 2021-10 -> 2022-04 delayed by 6 months
2021-07
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2021-07 -> 2021-10 delayed by 3 months
2021-04
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2020-11
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (L) Regulatory approvals pending. Not under construction