Ash Creek BESS πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-04 |
Construction start |
|
Operation start |
|
Estimated start |
2028-03 |
Construction time |
|
Capacity in MWh
612
π This is an estimate
Maximum Power in MW
306
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ ACTX BESS Project LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.349606255901264+-94.95198089749223
Coordinates
33.349606255901264, -94.95198089749223
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
979 / 66391
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-04
report):
Plant Name / State
Ash Creek BESS / TX
go live / power
2028-03 / 306MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66391 / BESS
Entity name / entity id
ACTX BESS Project LLC / 65410
Changes:
2024-07
date: 2025-05 -> 2028-03 delayed by
34 months