Gateway Energy Storage System πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california / East Otey Mesa / San Diego
Dates
First heard 2020-09
Construction start 2019-09-01
Operation start 2020-07
Estimated start
Construction time 10 months -> 25 MWh/m
Capacity in MWh
250
Maximum Power in MW
250
Manufacturer
Type / Number of Packs / Cells
/ / LG
Customer / Owner / Developer
LS Power / Gateway Energy Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:32.570558+-116.910955
Coordinates
32.570558, -116.910955
βœ… Coords are exact (+/- 50m)
Notes

Project website
Sources
https://www.lspower.com/project-map/
https://vimeo.com/429223580
https://en.wikipedia.org/wiki/Gateway_Energy_Storage
Internal / External id
48 / 63834

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2021-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Gateway Energy Storage System / CA
go live / power
2020-07 / 250MW
status / status verbose
operation / operation
Plant id / generator id
63834 / GTWAY
Entity name / entity id
Gateway Energy Storage, LLC / 63512
Changes: