Elkhorn Battery Energy Storage System ππ€
Status
operation
Country / State / Closest City
πΊπΈ usa / california / close to santa cruz
Dates
First heard |
2020-09 |
Construction start |
2020-12 |
Operation start |
2022-04 |
Estimated start |
|
Construction time |
16 months -> 45 MWh/m
|
Capacity in MWh
730
Maximum Power in MW
182
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 256 /
Customer / Owner / Developer
PG&E / Pacific Gas & Electric Co. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.807971+-121.781701
Coordinates
36.807971, -121.781701
β
Coords are exact (+/- 50m)
Notes
in 2020, 64mwh were added
Project website
Sources
https://www.teslarati.com/tesla-megapack-battery-moss-landing-completion-video/
https://en.wikipedia.org/wiki/Tesla_Megapack
Internal / External id
7 / 62564
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Elkhorn Battery Energy Storage System / CA
go live / power
2022-04 / 182MW
status / status verbose
operation / operation
Plant id / generator id
62564 / ELKHO
Entity name / entity id
Pacific Gas & Electric Co. / 14328
Changes:
2022-06
status: construction -> operation πΎ π πΈ
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2022-05
date: 2022-03 -> 2022-04 delayed by
1 month
2022-03
date: 2022-01 -> 2022-03 delayed by
2 months
2022-02
date: 2021-12 -> 2022-01 delayed by
1 month
2021-12
date: 2021-11 -> 2021-12 delayed by
1 month
2021-11
date: 2021-10 -> 2021-11 delayed by
1 month
2021-10
date: 2021-08 -> 2021-10 delayed by
2 months
2021-09
date: 2021-07 -> 2021-08 delayed by
1 month
2020-12
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
date: 2021-03 -> 2021-07 delayed by
4 months