Oberon II Solar Project πŸ“ŠπŸ‘€πŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-08
Construction start 2022-12
Operation start 2023-09
Estimated start
Construction time 9 months -> 27 MWh/m
Capacity in MWh
250
πŸ“ This is an estimate
Maximum Power in MW
125
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ IP Oberon II, LLC / Intersect Power
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.718247+-115.35194
Coordinates
33.718247, -115.35194
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
https://www.pv-tech.org/us-government-approves-500mw-co-located-project-in-california-desert/
http://www.aspeneg.com/oberon-renewable-energy-project/
Internal / External id
702 / 65735

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-08 report):

Plant Name / State
Oberon II Solar Project / CA
go live / power
2023-09 / 125MW
status / status verbose
operation / operation
Plant id / generator id
65735 / OBIIB
Entity name / entity id
IP Oberon II, LLC / 64972
Changes:
2023-11
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2023-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2023-06
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-12
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete