Battle Mountain Solar Project πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / nevada /
Dates
First heard 2021-09
Construction start
Operation start 2021-06
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Consolidated Edison Development Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.48226633376159+-114.990143767415
Coordinates
41.48226633376159, -114.990143767415
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
232 / 61098

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2021-09 report):

Plant Name / State
Battle Mountain Solar Project / NV
go live / power
2021-06 / 25MW
status / status verbose
operation / operation
Plant id / generator id
61098 / BMBS
Entity name / entity id
Consolidated Edison Development Inc. / 56769
Changes: