SMT Mission LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-09
Construction start 2023-11
Operation start 2023-12
Estimated start 2023-11
Construction time 1 months -> 20 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ SMT Mission LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.454054+-95.413438
Coordinates
33.454054, -95.413438
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1070 / 66927

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-09 report):

Plant Name / State
SMT Mission LLC / TX
go live / power
2023-12 / 10MW
status / status verbose
operation / operation
Plant id / generator id
66927 / SMTMB
Entity name / entity id
SMT Mission LLC / 65839
Changes:
2024-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-01
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (TS) Construction complete, but not yet in commercial operation