Holly Branch Solar, LLC πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-07 |
Construction start |
|
Operation start |
|
Estimated start |
2027-08 |
Construction time |
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Holly Branch Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.35211785870876+-95.34749894178886
Coordinates
33.35211785870876, -95.34749894178886
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1033 / 66692
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-07
report):
Plant Name / State
Holly Branch Solar, LLC / TX
go live / power
2027-08 / 100MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
66692 / HOLY
Entity name / entity id
Holly Branch Solar, LLC / 65698
Changes:
2024-07
date: 2026-10 -> 2027-08 delayed by
10 months