Outer Cape Community Battery πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / massachusetts /
Dates
First heard |
2020-09 |
Construction start |
2020-12 |
Operation start |
2022-05 |
Estimated start |
|
Construction time |
17 months -> 2 MWh/m
|
Capacity in MWh
50
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Eversource /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:42.571152+-71.761147
Coordinates
42.571152, -71.761147
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
220 / 62604
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Outer Cape Community Battery / MA
go live / power
2022-05 / 25MW
status / status verbose
operation / operation
Plant id / generator id
62604 / OCESS
Entity name / entity id
Eversource / 59497
Changes:
2022-07
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
date: 2022-06 -> 2022-05
accelerated by 1 month
2022-06
date: 2022-04 -> 2022-06
delayed by 2 months
2022-01
date: 2021-12 -> 2022-04
delayed by 4 months
2021-12
date: 2021-11 -> 2021-12
delayed by 1 month
2021-11
date: 2021-09 -> 2021-11
delayed by 2 months
2021-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-05
date: 2021-03 -> 2021-09
delayed by 6 months
2020-12
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete