Alpaugh BESS πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2025-07
Construction start
Operation start
Estimated start 2025-12
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ RWE Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.872677+-121.300049
Coordinates
40.872677, -121.300049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1775 / 68954

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-07 report (Project first appeared in the 2025-07 report):

Plant Name / State
Alpaugh BESS / CA
go live / power
2025-12 / 10MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
68954 / ALPHB
Entity name / entity id
RWE Clean Energy / 67192