Alfred Oaks Solar, LLC πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / new york /
Dates
First heard |
2023-07 |
Construction start |
|
Operation start |
|
Estimated start |
2026-05 |
Construction time |
|
Capacity in MWh
40
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Alfred Oaks Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:42.815588720802765+-75.55669092303249
Coordinates
42.815588720802765, -75.55669092303249
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1026 / 66675
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-07
report):
Plant Name / State
Alfred Oaks Solar, LLC / NY
go live / power
2026-05 / 20MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66675 / BA
Entity name / entity id
Alfred Oaks Solar, LLC / 65689