Sunrose Renewable Energy πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2024-11
Construction start
Operation start
Estimated start 2027-12
Construction time
Capacity in MWh
600
πŸ“ This is an estimate
Maximum Power in MW
300
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Vesper Energy Development LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.21620300365377+-95.10062913582601
Coordinates
33.21620300365377, -95.10062913582601
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1577 / 68033

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-11 report):

Plant Name / State
Sunrose Renewable Energy / TX
go live / power
2027-12 / 300MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
68033 / SRSEB
Entity name / entity id
Vesper Energy Development LLC / 64545
Changes: