Lake Mabel Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / florida /
Dates
First heard 2023-07
Construction start 2024-03
Operation start
Estimated start 2025-01
Construction time
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Tampa Electric Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:30.181357961192568+-82.0795645724725
Coordinates
30.181357961192568, -82.0795645724725
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1022 / 66641

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-07 report):

Plant Name / State
Lake Mabel Storage / FL
go live / power
2025-01 / 40MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
66641 / BESS1
Entity name / entity id
Tampa Electric Co / 18454
Changes:
2024-04
date: 2024-12 -> 2025-01 delayed by 1 month
2024-03
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete